Nigeria reports over 6,000 local jobs on Kano–Maradi railway
A 20 November ministry update reports more than 6,000 Nigerian workers and progress on railway sleepers. The December target covers the Kano–Katsina section, not the entire cross-border line.
More than 6,000 Nigerians are working on the Kano–Katsina–Maradi railway project, according to a transport ministry update issued after a 20 November inspection at Kazaure in Jigawa State. Permanent Secretary Funso Adebiyi put the total workforce at about 6,500, including roughly 200 expatriates.
Adebiyi said around 650,000 of the planned 800,000 concrete sleepers had been produced at the construction yard. Sleepers support the rails; their production is a construction milestone and does not by itself show that the whole railway is operational.
The government continues to target December 2026 for commissioning the Kano-Dawanau to Katsina section. Work would continue on the links from Katsina through Jibia to Maradi in Niger. New Telegraph's reporting of the inspection separately put the target for the full line at December 2027.
The ministry also said discussions with Niger's transport authorities had resumed over security, immigration and customs arrangements for moving construction equipment and personnel across the border.
Nigeria's economic context: FXRates' assessment is that the reported local employment and on-site production are immediate economic channels. Any wider freight, trade or passenger benefits depend on completed infrastructure and workable services. The announcement does not establish that cross-border operations have begun, nor does it provide measured reductions in transport costs. The opening dates remain government targets.